Installation method of Hastelloy reactor

Release date:2025-02-22Number of views:1050

The installation of Hastelloy reactor is a relatively complex but crucial process, the following are some detailed installation steps and precautions:

Installation procedure

‌ Preparatory work ‌ :

Make sure the reactor and its accessories (such as agitator, seals, etc.) are in good condition.

Clean the installation site to ensure that the workbench is strong, flat, and has enough space for installation and later maintenance.

‌ Mounting chassis and support structure ‌ :

If the reactor is equipped with a chassis and movable components (such as pulleys), ensure that they are securely installed, easy to move and increase stability.

‌ Install sealing jacket and reducer ‌ :

Remove reactor clamp, install sealing jacket and tighten screws.

Install the reducer and fix the four screws, and then install the reducer bracket screws.

‌ Install agitator ‌ :

Remove the lock nut and stop ring of the agitator, insert the lock nut into the output shaft of the reducer support, and clamp the stop ring.

Clean the mechanical seal PTFE sealing surface to ensure that it is free of dust and scratches, and then place it in the water jacket.

Disassemble the agitator to check whether it is in good condition, then slowly insert it through the center hole of the kettle cover, and turn the agitator counterclockwise until it stops turning. Note that the output shaft of the reducer cannot follow the rotation.

‌ Assembling reactor ‌ :

Align the cover with the body of the reactor and tighten the clamp.

Adjust the mechanical seal of the water jacket, ensure that the clearance around the blender is uniform, and tighten the screws holding the water jacket diagonally.

Install the sealing pressure ring, and pad the rubber or cloth inside the pressure ring, and adjust the clearance of the pressure spring on the mechanical seal to the appropriate position (such as about 5 mm).

‌ Electrical and control system connection ‌ :

Connect all wires, including the power cord, the electric furnace wire between the controller and the kettle, the motor wire, and the temperature sensor and tachometer wire.

Check that the movable parts and fixed contacts on the panel and rear panel are normal, and ensure that the connectors are in good contact.

‌ Debugging and inspection ‌ :

Close the air main switch and set various parameters on the digital display table (such as upper alarm temperature, working temperature, etc.).

Press the "heating" and "stirring" switch, debug, observe the motor rotation, ensure no noise or friction sound.

Perform air tightness check to ensure that there is no leakage in each connection.

Matters needing attention

‌ security ‌ :

During installation and use, the safety operation procedures should be strictly observed to ensure the safety of personnel and equipment.

The equipment should be installed in a well-ventilated room, and ensure that the operation area has sufficient exits and passageways.

‌ Accuracy ‌ :

When installing, ensure that the drive shaft is perpendicular to the ground level, and the non-perpendicality shall not be greater than 1/1000 of the total height of the equipment.

The connecting parts and transmission parts should be firm and reliable, and the connecting pipes, pipe mouths, seals, etc., should be airtight test.

‌ Maintainability ‌ :

Check the operation of the equipment regularly, replenish the lubricating oil and replace the medium oil in time.

Regular inspection and maintenance of safety valves, pressure gauges, temperature gauges, etc.

‌ Professional ‌ :

Installation and commissioning should be carried out by professionals to ensure the best performance and safety of the equipment.

Hastelloy reactor is widely used in chemical industry because of its high temperature, high pressure and corrosion resistance. In the installation and use process, the material characteristics and working environment should be fully considered to ensure the long-term stable operation of the equipment.


CONNECT

The company is located in the south park of Jingjiang Economic and Technological Development Zone, with superior geographical location and convenient transportation.

  • Add:No.9 Lianshan Road, Chengnan Park, Jingjiang

    View map

  • Contact:Sang Yuanliang

    Tel:13338894168 

  • Scan code browse mobile website!